Page 163 - Annual Report 2022 - PLN Indonesia Power
P. 163
Profil Perusahaan
Company Profile
Kronologis Pencatatan Efek Lainnya
Other Securities Listing Chronology
Sampai dengan 31 Desember 2022, PLN Indonesia Power telah Until December 31, 2022, Indonesia Power has appropriated
mempergunakan dana sekuritisasi EBA pada proyek-proyek EBA securitization funds in the following business development
pengembangan usaha berikut: projects:
31,86% 16,34% 13,76% 12,81%
Total Disburse:
Rp 4 Triliun
Rp 4 Trilion
PLTGU Grati Add On PLTU Kaltim (1 x 27 MW) PLTGU Tambak Lorok PLTU Suralaya 9 - 10
Blok 2 (183 MW) SPP East Kalimantan Blok III (779 MW) (2x1000 MW)
CCPP Grati Add On (1 x 27 MW) CCPP Tambak Lorok SPP Suralaya 9 - 10
Block 2 (183 MW) Block III (779 MW) (2x1000 MW)
11,11% 9,46% 4,12% 0,55%
Rp2,5 T Rp1,5 T
Mobile Power Plant PLTU Kalbar-1 PLTD Senayan PLTA Poigar (30 MW)
(MPP) Papua (2x100 MW) (101 MW) dan beberapa
(120 MW) SPP West Kalimantan-1 DPP Senayan (101 MW) pembangkit lain
2017 2018 (2x100 MW) HPP Poigar (30 MW) and
several other plants
Dari beberapa proyek yang mempergunakan dana sekuritisasi EBA Of projects which appropriated EBA securitization funds, SPP East
tersebut, PLTU Kaltim-1 kapasitas 2x27,5 MW di Muara Jawa telah Kalimantan-1 with capacity of 2x27.5 MW in Muara Jawa has been
beroperasi tanggal 1 Desember 2018, PLTD Senayan kapasitas 101 in operation since December 1, 2018, DPP Senayan with capacity of
MW telah beroperasi pada 5 Desember 2019 serta PLTGU Grati 101 MW has been in operation since December 5, 2019, CCPP Grati
Add On Blok 2 kapasitas 183 MW telah beroperasi pada 30 Juni Add On Block 2 with capacity of 183 MW has been in operation
2020 dan PLTU Kalbar 1 (Unit 1 dan 2) berkapasitas 2x100 MW since June 30, 2020, and SPP East Kalimantan 1 (Unit 1 and 2) with
telah beroperasi pada tanggal 3 Februari 2021 dan 25 Juni 2021. capacity of 2x100 MW have been in operation since February 3,
Selain itu, Mobile Power Plant Papua di beberapa lokasi juga 2021 and June 25, 2021. In addition, Mobile Power Plant Papua in
telah beroperasi, antara lain MPP Sorong kapasitas 50 MW, MPP several locations have been in operation, such as MPP Sorong with
Biak kapasitas 10 MW, MPP Merauke-2 kapasitas 20 MW, MPP capacity of 50 MW, MPP Biak with capacity of 10 MW capacity,
Manokwari-2 kapasitas 20 MW, MPP Timika kapasitas 10 MW, dan MPP Merauke-2 with capacity of 20 MW, MPP Manokwari-2 with
MPP Nabire kapasitas 10 MW. Di tahun 2022, PLN Indonesia Power capacity of 20 MW, MPP Timika with capacity of 10 MW, and MPP
sedang dalam proses pembangunan PLTGU Tambak Lorok Blok 3 Nabire with capacity of 10 MW. Starting in 2022, Indonesia Power
berkapasitas 779 MW yang direncanakan akan mulai beroperasi has been constructing CCPP Tambak Lorok Block 3 with capacity of
secara komersial pada Juni 2023 sedangkan PLTU Suralaya 9-10 779 MW. This power plant will operate commercially in June 2023,
diestimasi COD pada 2027 sesuai RUPTL. while estimated COD for SPP Suralaya 9-10 is 2027 according to
Electricity Supply Master Plan (RUPTL).
2022 Annual Report
www.plnindonesiapower.co.id 163